2018 Street Rehabilitation Project

Description

This project consists of rehabilitation of streets at various locations throughout the City of Windsor Heights, that includes approximately 13,000 feet (30 blocks) of hot mix asphalt (HMA) overlay along with concrete street patching.  The following streets are proposed to have HMA overlay:

  • 69th Street between Washington Avenue and Hickman Road
  • Northwest Drive between 69th Street and Franklin Avenue
  • Allison Avenue between 66th Street and 64th Street
  • 66th Street between south end and Lincoln Avenue
  • 66th Street between School Street and University Avenue
  • 70th Street between University Avenue and Colby Avenue

The project also includes concrete street patching on:

  • 70th Street between Colby Avenue and Hickman Road

2018 Street Rehabilitation Project Map                                                               

Estimated Start Date

  • April 16, 2018

Estimated Completion Date

  • August 31, 2018

Estimate and Costs

  • $1,130,500

Contractor(s)

  • TBD

Engineer

  • Matt Ferrier and Justin Ernst, Bolton & Menk  515-259-9190

City Staff Project Contact

  • Public Works Director Dalton Jacobus 515-645-6825


Project Status

 HMA Overlay:

  • The Contractor will begin work on April 30th: 
    • · Northwest Drive and 64th Street between 69th Street and Allison Avenue- Completed
    • · Allison Avenue between 66th Street and 64th Street- Completed
    • · 66th Street between Lincoln Avenue and south end of road- Completed
  • The Contractor will be pouring curb on Northwest Drive and 64th Street the week of May 21st.  The remaining streets on the project (66th Street, 69th Street, and 70th Street) are on hold until Des Moines Water Works complete their project which is the anode retrofit project more details are coming soon.

  • If it rains on the day scheduled for the asphalt overlay, the contractor will place the overlay on the next business day. Once the milling of the street begins, please do not park cars on the street until after the overlay has been placed. The contractor will be sweeping and cleaning the street between the milling and the asphalt placement. Those properties affected will receive notice from the contractor.
    .