2018 Street Rehabilitation Project

Description

This project consists of rehabilitation of streets at various locations throughout the City of Windsor Heights, that includes approximately 13,000 feet (30 blocks) of hot mix asphalt (HMA) overlay along with concrete street patching.  The following streets are proposed to have HMA overlay:

  • 69th Street between Washington Avenue and Hickman Road
  • Northwest Drive between 69th Street and Franklin Avenue
  • Allison Avenue between 66th Street and 64th Street
  • 66th Street between south end and Lincoln Avenue
  • 66th Street between School Street and University Avenue
  • 70th Street between University Avenue and Colby Avenue
  • Mott – 69th Street to 66th Street
  • School St – 64th to 65th
  • 65th St – School to Lamar Pl
  • Lamar Pl – 65th to 64th St

The project also includes concrete street patching on:

  • 70th Street between Colby Avenue and Hickman Road

2018 Street Rehabilitation Project Map                                                               

Estimated Start Date

  • April 16, 2018

Estimated Completion Date

  • August 31, 2018

Estimate and Costs

  • $1,130,500

Contractor(s)

  • TBD

Engineer

  • Matt Ferrier and Justin Ernst, Bolton & Menk  515-259-9190

City Staff Project Contact

  • Public Works Director Dalton Jacobus 515-645-6825


Project Status

HMA Overlay:

The Contractor will be completing punch list items for the overlay project week of November 5th.  All work is weather dependent.

Patching Project:

The Contractor will be applying pavement markings on 70th Street between Colby Avenue and Hickman Road the week of November 5th. Please follow traffic control signs to provide a safe work environment. All work is weather dependent.