Sunset Terrace Project

Description

This project consists of reconstruction of streets, sewers, and water main from 6500 Sunset Terrace to 73rd Street.  Phases 1-4.

Contract Amount

  • $1,497,275.60


Estimated Start Date

  • Phase 1 complete December, 2016
  • Phase 2-4:  Start March 27, 2017


Estimated Completion Date

  • August 31, 2017

Contractor(s)

  • Sternquist Construction, 515-975-3642


Engineer

  • Matt Ferrier and Justin Ernst, Bolton & Menk  515-259-9190


City Staff Project Contact

  • Public Works Director Dalton Jacobus 515-645-6825

Project Status

  • The Contractor will be completing punch list items on Sunset Terrace the week of November 5th.  
  • All work is weather dependent.
  • The Contractor plans to work Saturdays if weather permits.  All work is weather dependent.


Any questions call Wyatt Klooster, Bolton & Menk, at 563-249-1719. He will assist you with the process.