14 Oct 2016

PHASE 1 CONSTRUCTION UPDATE 10-14-2016:

The Contractor has completed the installation of the subdrain this week.  The Contractor will be paving the driveways on Monday and Tuesday.   Wednesday will be a cleanup day.  Seeding will take place on Thursday and Friday.   We have changed our approach for seeding and have decided to proceed with a permanent seed mix with the understanding that it is likely that the contractor will be required to return in the spring to overseed.  By next weekend, weather depending, Sunset Terrace Phase 1, should be open to traffic.  Thank you to all of you for your patience during this construction project.