16 Sep 2016

PHASE 1 CONSTRUCTION UPDATE 09-16-2016:

All underground work has been completed.  Compaction testing will be completed during the first part of next week.  The end of the week the Contractor will be trimming the subgrade in preparation of paving.  The Contractor is anticipating paving Phase 1 at the end of next week/beginning of the following week. The Contractor has also provided an updated schedule for distribution, which is attached.

If you experience any utility or construction issues, please refer to the attached diagram for reference to whom you should contact.   These will remain in effect for the rest of the phases when they commence.

 