02 Aug 2016

Phase 1 Road Closure Update

Due to today’s rain the Contractor feels that the ground is too wet to begin pavement removal tomorrow as scheduled.  They will plan to start the removals on Thursday (8/4).  Therefore you have an additional day before the roadway closes to traffic.  Also the Contractor has stated that the courtesy cart is on site and will be ready for Thursday.  Please contact me if you have any additional questions.  Thanks.

.