22 Aug 2016

PHASE 1 CONSTRUCTION UPDATE 08-19-2016:

All the sewer laterals under the roadway have been completed and the Contractor is currently working on completing the water main service connections.  The water service transfers will take all of next week to finish.  Due to recent events the schedule has been pushed back a week and the completion date is now September 23rd.  The updated schedule has been included with this update.

Courtesy Cart Usage

The courtesy cart is available for Phase 1 residents for use while the roadway is closed.  The courtesy cart (golf cart) is available to transport residents to and from their parked vehicles to their residences while the roadway is closed to vehicular traffic.  The courtesy cart contact phone number is (515) 975-2749.  The cart is available Monday through Friday from 7 am through 5 pm and on Saturday from 7 am through 12 pm. 

Garbage collection during roadway shutdown –

Please place your trash can at the end of your driveway as you would have normally done and the contractor will take care of getting it to a spot that the pickup service will collect it.  Then the contractor will return your trash can after collection to the end of your driveway.  The contractor will put a temporary sticker/tape on it to mark the address so they will not get mixed up. 

Please check on the City’s website and Facebook page for updates, including the Contractor’s most current schedule, as they become available. The schedules will be included with the updates only if they have changed. 

 

PROJECT CONTACT NUMBERS AND EMAILS (SAVE FOR FUTURE REFERENCE)

 

MSA Professional Services          

1.)    Nichole Sungren, Project Manager          515-635-3404 (Office), 515-205-0883 (Cell)

nsungren@msa-ps.com

2.)    Jason Miller, Secondary Contact                                515-635-3402 (Office), 515-979-5540 (Cell)

jmiller@msa-ps.com

3.)    Richard Harris, Project Inspector               515-291-3500 (Cell)

4.)    Justin Pettit, Project Inspector                   309-333-8937 (Cell)

 

Sternquist Construction (Prime Contractor, Paving)

1.)    Brad Freeman, Project Manager               515-961-8127 (Office), 515-975-3642 (Cell)

bfreeman@sternquistconstruction.com

 

JRS Excavating (Sub Contractor, Utilities)

1.)    Ethan Williams, Project Foreman              515-250-4924 (Cell)

jrsexcavating@hotmail.com

 

City of Windsor Heights

1.)    Doug Stone, Public Services Director       515-645-6825 (Office), 515-402-3208 (Cell)

dstone@windsorheights.org

 

Schedule Update