03 Oct 2016

PHASE 1 CONSTRUCTION UPDATE 10-03-2016:

The Contractor paved Phase 1 on Saturday.  The contractor will seal the pavement on Tuesday and install subdrain on Wednesday and Thursday.  Weather permitting, driveway paving will begin on Friday along with the caps for the sewer laterals for Phases 2 and 3.  Backfill behind the curb and surface restoration will follow.   Seeding will be a temporary mix since we are now out of the allowable permanent seeding dates.  The contractor will be required to return in the spring to reseed with the permanent mix.