Sunset Terrace Project

Description

This project consists of reconstruction of streets, sewers, and water main from 6500 Sunset Terrace to 73rd Street.  Phases 1-4.

Contract Amount

  • $1,497,275.60


Estimated Start Date

  • Phase 1 complete December, 2016
  • Phase 2-4:  Start March 27, 2017


Estimated Completion Date

  • August 31, 2017

Contractor(s)

  • Sternquist Construction, 515-975-3642


Engineer

  • Matt Ferrier and Justin Ernst, Bolton & Menk  515-259-9190


City Staff Project Contact

  • Public Works Director Doug Stone 645-6825

Project Status

  • All work is weather dependent, including heat.
  • The Contractor plans to work Saturdays if weather permits.  All work is weather dependent.


70th Street to 73rd Street

The Contractor will begin pavement removal the week of August 7th. Once all the pavement is removed, they will begin the installation of the new watermain on the south side of the street. Those residents living in affected areas will receive a letter pertaining to construction in the coming days.


66th Street to 68th Street

The Contractor will be installing subdrain along both sides of the street the week of August 14th along with pouring driveways the middle of the week and restoration. The driveways will need time to cure before vehicle traffic is allowed on the them, approximately 7-10 days.


Additional Resources